Sharon Road sidewalk

  • Project typeStreets and sidewalks
  • Completion dateAugust 31, 2022
15-mph-school-zone-speed-sign-and-completed-Sharon-Road-sidewalk.jpg

Construction commenced this June and was finished by August. As of September 2022, the project improvements are installed and opened for the public. 

On May 10, 2022 the City Council awarded the project's construction contract to Granite Rock Company.

On Dec. 7, 2021, the City Council approved designs for a 5-foot wide sidewalk along the 2100 block of Sharon Road. The approved design also includes 10 to 11-foot travel lanes within the project limits. Thereafter, staff finalized the project’s construction drawings and solicited construction bids in April 2022. 

On Jan. 26, 2021, the City Council selected a raised concrete sidewalk as the preferred alternative on Sharon Road, from Alameda de las Pulgas to Altschul Avenue. The project was then on hold until December 2021 due to litigation.

Contact us

Michael Fu
Senior Civil Engineer
Email

650-330-6706

Location

2100-2200 Sharon Road, Menlo Park, CA 94025  View map