Project background and timeline
- April 4 2023 – City Council receive informational report about the project
- April 26 2023 – Parks and Recreation Commission reviewed and provided feedback to the project plans
- May/June 2023 - Additional stakeholder outreach including casual park users, MPCC Subcommittee and working group
- Jan 2024 – Design documents finalized
- March 2024 – Construction Contract
- April 2024– City Council award of construction contract
- September 2024 – Construction begin pending Microgrid construction completion at the new multi-service center facility
- November 2024 – Construction complete