Menlo Park Community Campus foundation pour set for March 5

Published on February 18, 2022

MPCC-Concrete-Truck-Route-Exhibit

Level 10 Construction will pour the building foundation for the city’s new community campus, located at 100 Terminal Ave., on Saturday, March 5, 2022. Completing the building’s foundation is a key project milestone as we work toward the facility’s opening date in 2023.

The City of Menlo Park and Level 10 Construction have carefully planned and coordinated this phase of work.

  • To reduce impacts to residents, work will take place 3 a.m. to 4 p.m., Saturday, March 5.
  • An exception to the city noise ordinance is needed for work from 3–9 a.m.
  • Concrete pumps will setup at 3 a.m., ahead of the first concrete truck arriving at 4 a.m.
  • Concrete trucks will travel along the approved truck route (attached).
  • We estimate that 2,900 yards of concrete are needed.
  • A street sweeper will work during the pour to help keep city streets clean.

Kelly Park will remain open to the public throughout the work. Flaggers stationed at the site will help pedestrians and vehicles safely enter and exit the park.

For this day, we recommend that visitors park on nearby streets and walk to Kelly Park, as on-site parking will be limited.

View the foundation pour notice letter and concrete truck route map(PDF, 1MB)  to be provided to nearby residents